JOC ARCHIVES

June 22, 2009

Wood may be the prominent feature in the finished Richmond Speed Skating Oval but steel gives it the underlying strength. It has 15 glulam pine and steel arches.

Wood may be the prominent feature in the finished Richmond Speed Skating Oval but steel gives it the underlying strength. It has 15 glulam pine and steel arches.

Wood may be the prominent feature in the finished Richmond Speed Skating Oval but steel gives it the underlying strength. It has 15 glulam pine and steel arches.

Structural Steel

Wood and steel are a unique marriage at skating oval for Vancouver’s 2010 Olympics

Wood is the most prominent feature of the 2010 Olympic Winter Games speed skating oval, but steel trusses provide its structural strength.

The Olympic oval is part of the City of Richmond’s $178-million arena on the shores of the Fraser River.

George Third and Sons (GTS) of Port Coquitlam handled the $12-million contract to supply and install the structural steel, most of it used on the building’s 15 steel-and-glulam roof arches.

The innovative design called for the contractor to create 60 massive V-shaped arched trusses married to glulam pine.

Each of the 18-tonne truss sections measured about 26 metres long and required 250,000 screws to assemble.

GTS began the project in October 2006.

The trusses were manufactured by Dynamic Structures of Port Coquitlam, a company owned by GTS, while the laminated wood portion of the trusses were fabricated by Structurlam Products of Penticton.

“We were definitely faced with a very demanding schedule, and there were many challenges marrying wood to steel,” said Ziggy Welsch, project manager for GTS.

“The steel is obviously stronger and more forgiving than the brittle wood, so more thought had to go into fit-up procedures and handling. We had to protect the wood wherever we were welding to prevent damage to the wood glulam beams. The assembly took up a lot of our shop space and the extremely complicated geometry to fabricate the two glulam beams into a V-truss to form the radius was the biggest challenge.”

Each of the 60 completed truss sections were shipped to site one at a time on a trombone trailer.

On site they were covered to help protect them from moisture, as well as UV rays, which could damage painted areas and fade the wood glulam.

A 200-ton crane was used to lift the truss sections into place.

“First the two end pieces were lifted into position supported by heavy-duty steel towers bearing the ends of the trusses,” said Welsch.

“Next, the two middle sections were assembled and spliced together on the concrete slab and lifted into place as one to fill the void in the middle. Jacking against the concrete buttress, the field crew pushed the trusses together until our final required positioning was achieved and then the ends were filled with a high-strength grout to complete the span of approximately 100 metres.”

The fabricating company also manufactured a series of curved steel beams that decorate the exterior edge of the roof.

Johnston Architects Inc., principal and lead project architect, designed the beams to reflect the blue heron, a bird that nests in the area.

“The complicated twisted wide flange beams at the north end of the building are highly visible and simulate a heron feather,” said Welsch.

“These were not only challenging to fabricate in our shop, but also to erect. With the help of our seasoned field crew we managed to push, pull and pry the steel into position.”

The Olympic Oval has already won a prestigious Award of Excellence in For Architectural Innovation from the Royal Architectural Institute of Canada.

The jury praised the structure for its innovative use of pine beetle-killed wood spanning, what it called, the elegant roof.

It also praised the seamless integration of the mechanical systems, as well as the building’s transparency, which maximizes daylight.

In addition to the use of one million board feet of pine-beetle wood in the ceiling, which the jury called stunningly beautiful, they were also impressed with the Oval’s innovative use of glulam beams spanning almost 100 metres, to creatively integrate with the ceiling.

As such and ironically, most of the structural steel employed in the creation of the skating oval will be invisible to the thousands of Olympic fans filling the stadium in 2010.

“I must say by now we’re used to being covered up,” said Welsch.

“The important thing is we know that without our steel these trusses could not have been possible. It’s a combined effort and all of us involved with this once-in-a-lifetime project feel very proud to have contributed to its success.”

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 263 projects with a total value of $8,919,878,049 that Reed Construction Data Building Reports reported on yesterday.

NATURAL GAS PROCESSING FACILITY

$500,000,000 Fort Nelson BC Prebid

NATURAL GAS PLANT

$250,000,000 Fort Nelson BC Negotiated

HOSPITAL ADDN

$35,000,000 Winnipeg MB Prebid

Daily Top 10

ALEX’S ECONOMICS BLOG

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

Project Manager - Electrical Construction
Ontario-Richmond Hill

Traffic Manager / Dispatcher
Ontario-Mississauga

PROJECT MANAGERS & SUPERINTENDENTS
Ontario-Toronto

Surveyor/Layout Person
Ontario-Toronto

Senior Project Manager/Estimator
British Columbia-Delta

Chief/Senior Estimator
Ontario-Brampton

Senior Estimator
British Columbia-Vancouver

Contracts Manager
Ontario-Mississauga

Heavy Duty Equipment Mechanic
Manitoba-Flin Flon

Heavy Duty Equipment Mechanic
Manitoba-Thompson

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design